MERITON APARTMENTS BASEMENT

Rosebury, NSW

CFA Piles, Anchors

Project Description
The project required a large shoring wall to construct a one level basement for a set of residential apartments in Rosebery. The shoring wall consisted of 400 number 600mm diameter CFA piles with 28 number anchors along the Eastern Wall and a shotcrete finish all around for an aesthetic appeal.
Solutions

CFA piling technique was utilised to install the piles on site due to the geotechnical conditions present. This provided for very high production rates of around 180 lineal metres per day of pile installation.

Apartments

Meriton Pty Ltd

Bachy Soletanche Australia

Date

Client

Industry

Engineer

April 2016 - August 2016