NACC WILLIAMTOWN RAAF BASE UPGRADE

Williamtown, NSW

CFA Piles & Foundation Piles

3.jpg
20160205_083123_Felix St LR.jpg
20160205_083123_Felix St LR.jpg
Project Description
Design and Construct 84 no. foundation piles for the new air force base aeroplane hangars. CFA Piling of 750mm diameter piles at 10m depth.
Solutions

Drilling needed to be closely monitored by the operator and supervisor when the pile had reached final depth. At this point, concreting commenced and the auger was held in position briefly before retracting to allow a firm, and clean base for the toe of the pile and a smooth extraction rate for the auger.

Industry

Airport

Client

Defence Support Group

Date

April 2016 - July 2016

Engineer

Bachy Soletanche Australia