SYDNEY FOOTBALL STADIUM (SFS)

Sydney, NSW

Bored Piles

SYDNEY FOOTBALL STADIUM (SFS)
Bored Piles
Bachy Soletanche Australia was proud to be appointed the piling contractor for the new Sydney Football Stadium. We had four piling rigs and one anchoring machine working simultaneously to install the foundations for Sydney’s next world-class sporting and entertainment venue.

BSA provided a complete Design and Construct solution incorporating approximately 1500 CFA piles drilled through sand to found in bedrock to maximum depths of 33m. Pile integrity and dynamic load testing was conducted to successfully verify our design and construction methods.

A team effort with clients John Holland and the NSW Government ensured the safe and timely delivery of the foundations on multiple work fronts.
Project Description
Bachy Soletanche Australia was proud to be appointed the piling contractor for the new Sydney Football Stadium. We had four piling rigs and one anchoring machine working simultaneously to install the foundations for Sydney’s next world-class sporting and entertainment venue.

BSA provided a complete Design and Construct solution incorporating approximately 1500 CFA piles drilled through sand to found in bedrock to maximum depths of 33m. Pile integrity and dynamic load testing was conducted to successfully verify our design and construction methods.

A team effort with clients John Holland and the NSW Government ensured the safe and timely delivery of the foundations on multiple work fronts.
Solutions

Design and Construction of CFA foundation and contiguous pile retaining wall with temporary soil anchors.

Key figures for the project:

More than 20 km continuous flight auger (CFA) piles drilled

More than 10.000 cubic metre concrete placed

Maximum pile diameter: 900mm

Maximum pile depth: 33m

Industry

Infrastracture, Spoting Venue

Client

John Holland Group

Date

May 2020 - November 2020

Engineer

Aurecon