SYDNEY METRO
Sydney, NSW
Plunge Column in Bored Piles
Project Description
Bachy Soletanche Australia has been appointed the role of piling contractor as part of a $955 million contract with Sydney Metro to improve the busiest transport hub in Australia. Bachy Soletanche Australia (BSA) will be installing 279 Bored Piles and 42 Plunge Columns at Sydney Metro, Australia’s busiest transport hub.
Solutions
Temporary works design, manufacture and fabrication of plunge column frame.
Key requirements for the project:
-
Verticality: 1 in 250
-
Positional tolerance: 20mm
-
Rotational: 2deg >3.5m below platform level
-
Plunge column lengths up to 27.0m
-
Incorporation of plunge column pile cages
-
Tight installation tolerances for cages and columns
-
Working adjacent to a live railway station
Industry
Rail
Client
Transport for NSW
Date
December 2018